After just over a nine-month closure of Bow Hill Road between Darrk Lane and Old Highway 99 North, the road opened to traffic on the afternoon of April 21, 2022.
The reconstruction project installed four new concrete faced soil nail retaining walls along the north side of the road, transferred the overhead utilities to underground, and installed a new soldier pile retaining wall along the south side of the road. Additional work included new storm drainage piping, new guardrail, and new asphalt.
We are excited to complete construction activities approximately one month early and appreciate the community’s patience throughout the duration of the project.
For more information visit the Public Works project webpage Bow Hill Road Reconstruction (www.skagitcounty.net/Departments/PublicWorksEngineering/BowHillproject.htm).